Mississippi Private Time Frames


Step 1: Notice
  • Commercial: Lien claimants without a direct contract with the prime contractor or, in the instance that there is no prime contractor owner; serve within 30 days of first furnishing.
  • Residential: Serve Pre-Lien Notice as soon as possible to trap funds.

Step 2: Lien
  • Residential: 10-day notification prior to lien filing; file within 90 days of last furnishing
  • Commercial: A claim of lien must be filed within 90 days after last furnishing.
  • Serve Owner and General Contractor within 2 days after recording.

Caution:  See WAIVER WIRE section for important statute detail within 60 days of signing a Waiver/Release when payment has not been received.


Step 3: Foreclosure
  • Within 180 days from the date of the filing of a claim of lien. A lis pendens notice shall be filed with the commencement of the action, with a copy provided to the owner and contractor as well.