New Hampshire Private Time Frames


Step 1: Notice
  • Subcontractors and Suppliers:
    • Serve the Owner: Notice of Intent to Lien as soon as possible (prior to furnishing) to trap unpaid funds.
    • Serve the Owner: A written account stating the current and total balance due (supply invoice copies) 30 days after the initial notice, and every 30 days thereafter. See Speed Bumps

Step 2: Lien
  • Within 120 days of last furnishing
  • Due to the unique nature of the statute NACM recommends commencing action no later than 80 days from last furnishing.

Step 3: Foreclosure
  • Within 120 days of last furnishing.